22-bogie train’s trial run successful on Katra-Srinagar line

- Advertisement -
- Advertisement -

JAMMU, Jan 19: A 22-bogie train chugged between Katra and Srinagar railway stations on Sunday, officials said, marking the first successful trial run on the newly completed line to connect Kashmir with the rest of the country via rail.

The train, comprising 18 AC coaches, two luggage carriers and two engines, left the Katra railway station at around 8 am, successfully reaching its destination within four hours under the watchful eyes of the railway authorities, the officials said.

- Advertisement -

This was the first trial run between Katra and Srinagar, and came within six days after the Commissioner of Railway Safety (Northern Circle) Dinesh Chand Deshwal authorised the opening of the newly constructed Broad Gauge line.

He had given the authorisation for the start of public carriage of goods and passenger traffic in a seven-page letter to the ministry and railway authorities, based on his detailed inspection of the track on January 7 and 8.

The CRS referred to his inspection of the newly constructed BG line between the Katra and Reasi section by a motor trolley and on foot, followed by a speed trial on the entire section from Katra to Banihal.

He had then authorised regular opening of the section for passengers and freight traffic at a maximum permissible speed of 85 Kmph on the main line and 15 Kmph on turnout.

- Advertisement -

The work on the dream project to link Kashmir by train was started in 1997 and it missed several deadlines given geological, topographical and meteorological challenges.

Out of the total 272 km  Udhampur-Srinagar-Baramulla Rail Link (USBRL) project, 209 km was commissioned in phases with the first phase of the 118 km Qazigund-Baramulla section commissioned in October 2009, followed by 18 km Banihal-Qazigund in June 2013, 25 km Udhampur-Katra in July 2014 and 48.1 km long Banihal-Sangaldan stretch in February, last year.

The work on the 46-km Sangaldan-Reasi section was also completed in June last year, leaving a total of 17 km stretch between Reasi and Katra. And this section was finally completed in December 2024 as announced by the Railway minister Ashwini Vaishnaw.

On January 4, a successful trial run of an electric train was successfully conducted on the Katra-Banihal section. The railways has conducted six trials over the past month on various segments of the track, including the two major milestones of the Anji Khad and Chenab bridges. (PTI)

- Advertisement -
The Hills Times
The Hills Timeshttps://thehillstimes.in/
Welcome to The Hills Times, your trusted source for daily news and updates in English from the heart of Assam, India. Since our establishment in 2000, we've been dedicated to providing timely and accurate information to our readers in Diphu and Guwahati. As the first English newspaper in the then undemarcated Karbi Anglong district, we've forged a strong connection with diverse communities and age groups, earning a reputation for being a reliable source of news and insights. In addition to our print edition, we keep pace with the digital age through our website, https://thehillstimes.in, where we diligently update our readers with the latest happenings day by day. Whether it's local events, regional developments, or global news, The Hills Times strives to keep you informed with dedication and integrity. Join us in staying ahead of the curve and exploring the world through our lens.
Latest news
- Advertisement -
Related news
- Advertisement -
Top Nutritious Food To Supports Your Health 6 Offbeat Places to Visit in Assam 10 Iconic Species To See In Nagarhole National Park 10 Places In Sikkim You Should Bookmark For Top 8 Lesser-Known Places In India To Spot Tigers